Project Details

PAVEMENT PRESERVATION (ASPHALT) DUE TO HARSH WINTER 23/24, JRP & BQE, QUEENS & KINGS COS.

Project ID No. XM2547 , Contract Number D265500

Description

This project will extend the service life of roadways on the Jackie Robinson Parkway and Brooklyn Queens Expressway in Kings and Queens counties of New York City by repairing asphalt pavement that is showing distress and deterioration due to normal wear and tear, aging and/or climatic conditions.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 06/26/2025

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
07/29/2025 11/15/2026 10/16/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$5,750,000 $0 $5,750,000 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the NEW YORK CITY region and includes the following:

Counties
KINGS
QUEENS

Cities
NEW YORK

11 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
5th Congressional District (Gregory Meeks)
6th Congressional District (Grace Meng)
7th Congressional District (Nydia Velazquez)
10th Congressional District (Daniel Goldman)
14th Congressional District (Alexandria Ocasio-Cortez)

State Senatorial District(s)
12th Senatorial District (Michael Gianaris)
14th Senatorial District (Leroy Comrie)
15th Senatorial District (Joseph P. Addabbo Jr.)
18th Senatorial District (Julia Salazar)
26th Senatorial District (Andrew Gounardes)

State Assembly District(s)
027th Assembly District (Sam Berger)
028th Assembly District (Andrew Hevesi)
034th Assembly District (Jessica Gonzalez-Rojas)
038th Assembly District (Jenifer Rajkumar)
051th Assembly District (Marcela Mitaynes)
054th Assembly District (Erik M. Dilan)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Rolando Infante
4740 21st Street, Room 860
Long Island City, NY 10038
Phone: 718-482-4528
Email: rolando.infante@dot.ny.gov
Provide feedback on this project