Project Details

CONCRETE PAVEMENT PRESERVATION, KINGS AND NEW YORK COUNTIES, NYC

Project ID No. XM1949 , Contract Number D263994

Description

This project will perform preservation of the concrete pavement on Rt. 9A (from Morris St. to W. 57th St.), the BQE entrance ramp (from Hamilton Ave.), and BQE eastbound and westbound (from Flushing Ave. to Wythe Ave.) to extend the service life of the pavement in New York and Kings Counties, NYC.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 06/20/2019

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
08/02/2019 12/20/2020 12/02/2020 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$10,141,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the NEW YORK CITY region and includes the following:

Counties
KINGS
NEW YORK

Cities
NEW YORK

11 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
7th Congressional District (Nydia Velazquez)
10th Congressional District (Daniel Goldman)
12th Congressional District (Jerrold Nadler)

State Senatorial District(s)
18th Senatorial District (Julia Salazar)
25th Senatorial District (Jabari Brisport)
26th Senatorial District (Andrew Gounardes)
27th Senatorial District (Brian Kavanagh)
47th Senatorial District (Erik Bottcher)

State Assembly District(s)
050th Assembly District (Emily Gallagher)
052th Assembly District (Jo Anne Simon)
057th Assembly District (Phara Souffrant Forrest)
061th Assembly District (Charles D. Fall)
066th Assembly District (Deborah J. Glick)
067th Assembly District (Linda B. Rosenthal)
075th Assembly District (Tony Simone)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Rolando Infante
4740 21st Street, Room 860
Long Island City, NY 10038
Phone: 718-482-4528
Email: rolando.infante@dot.ny.gov
Provide feedback on this project