Project Details

REPL K-BR OVER NEWTOWN CR-CONT 1. KGS & QNS COS, NYC

Project ID No. X73124 , Contract Number D900011

Description

This project is part of the Governor's NY Works Program. The Kosciuszko Bridge (East bound) over Newtown Creek from Morgan Ave to LIE interchange (Kings and Queens counties) will be replaced to ensure structural integrity, motorist safety, and to provide operational improvements. As per the Governor's NY Works Program, the K-Bridge project has been designated as a "signature project" .

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 12/04/2013

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
05/23/2014 12/31/2017 03/06/2018 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$554,770,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the NEW YORK CITY region and includes the following:

Counties
KINGS
QUEENS

Cities
NEW YORK

11 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
7th Congressional District (Nydia Velazquez)

State Senatorial District(s)
12th Senatorial District (Michael Gianaris)
18th Senatorial District (Julia Salazar)

State Assembly District(s)
037th Assembly District (Claire Valdez)
050th Assembly District (Emily Gallagher)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Rolando Infante
4740 21st Street, Room 860
Long Island City, NY 10038
Phone: 718-482-4528
Email: rolando.infante@dot.ny.gov
Provide feedback on this project