Project Details

BRP: REPLACEMENT OF 2 BRIDGES OVER E TREMONT AVE AND MTA YARD IN THE BRONX

Project ID No. X11029 , Contract Number D900059

Description

This project will replace two Bronx River Parkway (BRP) bridges (one bridge over East Tremont Ave and a second bridge over E. 180th St./Morris Park Ave/MTA rail yard) and make safety and mobility improvements between East Tremont Ave and Bronx Park (BINS 1067099 and 1067109) in Bronx Co. Additionally, a new bridge will be constructed to extend the interim lane of exiting traffic from S/B BRP to E. 177th St. (to be built under X11028) from E. Tremont Ave to Morris Park Ave. The project also includes wider standard lanes and shoulders, improvements to vertical and horizontal geometry, queuing storage space for exiting traffic, new stormwater drainage facilities, improvements to the safety of NYCDPR's Bronx River Greenway (BRG) and site drainage at the Ranaqua facility, and a shared use path from Bronx River Ave to the BRG in Bronx Park.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 02/02/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
05/31/2024 12/29/2027 11/29/2027 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$517,511,969 $0 $517,511,969 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the NEW YORK CITY region and includes the following:

Counties
BRONX

Cities
NEW YORK

11 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
14th Congressional District (Alexandria Ocasio-Cortez)
15th Congressional District (Ritchie Torres)

State Senatorial District(s)
32th Senatorial District (Luis R. Sepulveda)
33th Senatorial District (Gustavo Rivera)

State Assembly District(s)
087th Assembly District (Karines Reyes)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Rolando Infante
4740 21st Street, Room 860
Long Island City, NY 10038
Phone: 718-482-4528
Email: rolando.infante@dot.ny.gov
Provide feedback on this project