Project Details

BRIDGE CORRECTIVE REPAIRS & SAFETY IMPROVEMENTS AT WESTCHESTER AVE OVER SHERIDAN BLVD

Project ID No. X02709 , Contract Number D264280

Description

This project will implement low-cost safety and mobility improvements at Westchester Ave, between Home St and Edgewater Rd, over the Sheridan Expressway in Bronx County, NY. Improvements include: repaving and re-striping the pavement; providing lane assignment signs and object marker signs to help drivers navigate around the MTA NYCT subway columns; extending the bicycle lane pavement markings; bringing the curb ramps to ADA standards; improving roadway lighting; and adjusting the signal timings to reduce queueing on Westchester Ave and on the exit ramps from Sheridan Expwy. The project will also involve some substructure bridge corrective repairs.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 09/24/2020

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
11/13/2020 10/28/2021 03/17/2022 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,323,210 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the NEW YORK CITY region and includes the following:

Counties
BRONX

Cities
NEW YORK

11 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
14th Congressional District (Alexandria Ocasio-Cortez)

State Senatorial District(s)
32th Senatorial District (Luis R. Sepulveda)

State Assembly District(s)
085th Assembly District (Emerita Torres)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Rolando Infante
4740 21st Street, Room 860
Long Island City, NY 10038
Phone: 718-482-4528
Email: rolando.infante@dot.ny.gov
Provide feedback on this project