ADA ACCESSIBILITY PROJECT
Project ID No. 9ADA20 , Contract Number D264811
Description
This project is developed to remove and replace curb ramps and sidewalks that are not in compliance with the Americans with Disabilities Act (ADA). Various federal aid eligible Routes in Region 9. Town of Johnson City, Broome County. Village of Sherburne, Chenango County. Towns of Morris, Cherry Valley, Oneonta and Village of Richfield Springs, Otsego County. Towns of Middletown, Andes, Walton and Villages of Margaretville and Delhi, Delaware County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 12/15/2022
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 01/18/2023 | 12/08/2023 | 11/08/2023 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $2,428,698 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the SOUTHERN TIER region and includes the following:
Counties
BROOME
CHENANGO
DELAWARE
OTSEGO
Towns
ANDES
BUTTERNUTS
CHERRY VALLEY
DELHI
MIDDLETOWN
MORRIS
ONEONTA
RICHFIELD
SHERBURNE
UNION
WALTON
Villages
JOHNSON CITY
MARGARETVILLE
MORRIS
RICHFIELD SPRINGS
SHERBURNE
WALTON
CHERRY VALLEY
DELHI
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
51th Senatorial District (Peter Oberacker)
52th Senatorial District (Lea Webb)
53th Senatorial District (Joseph A. Griffo)
State Assembly District(s)
101th Assembly District (Brian Maher)
102th Assembly District (Chris Tague)
121th Assembly District (Joe Angelino)
122th Assembly District (Brian D. Miller)
123th Assembly District (Donna A. Lupardo)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov