Project Details

BRIDGE RAIL REPLACEMENT, REGIONWIDE, SFY 2025

Project ID No. 980774 , Contract Number D265683

Description

This project replaces deteriorated bridge rail systems, bridge railing tubes, and transition rail, if necessary, on 10 bridges throughout Region 9.  Any turning fork transitions and wrap around clamps are also replaced.

Issue Description:
This project will have accelerated design phases so that construction can begin in early 2026.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 01/22/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
03/03/2026 11/06/2026 11/06/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$1,305,348 $0 $1,305,348 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the SOUTHERN TIER region and includes the following:

Counties
BROOME
CHENANGO
OTSEGO

Towns
BAINBRIDGE
COLESVILLE
CONKLIN
GREENE
KIRKWOOD
MILFORD

09 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)

State Senatorial District(s)
51th Senatorial District (Peter Oberacker)

State Assembly District(s)
121th Assembly District (Joe Angelino)
122th Assembly District (Brian D. Miller)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 9 Regional Director's Office
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov
Provide feedback on this project