Project Details

I88 RESURFACING, EXIT 16 TO EXIT 17, OTSEGO COUNTY

Project ID No. 935854 , Contract Number D265744

Description

This contract resurfaces Interstate 88 and repairs failed transverse joints and pavement areas from Exit 16 to approximately one mile east of Exit 17 in the towns of Oneonta, Milford and Maryland, Otsego County.  Additional work includes new guide rail / median rail installation, ground-mounted sign structure upgrades and new pavement markings Safety Appurtenance Program (SAFETAP) items are also addressed as resources allow.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/26/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
05/05/2026 11/30/2027 10/30/2027 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$14,995,417 $0 $14,995,417 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the SOUTHERN TIER region and includes the following:

Counties
OTSEGO

Towns
MARYLAND
MILFORD
ONEONTA

09 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
51th Senatorial District (Peter Oberacker)

State Assembly District(s)
102th Assembly District (Chris Tague)
122th Assembly District (Brian D. Miller)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 9 Regional Director's Office
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov
Provide feedback on this project