RT 34 OVER KING HOLLOW CREEK
Project ID No. 931406
Description
This project either rehabilitates or replaces the structure carrying Route 34 over King Hollow Creek. Town of Barton, Tioga County
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2030/2031.
- Construction is expected to begin in Winter 2030/2031.
- Construction is expected to be completed in Summer 2031.
Cost of the Project
The project cost is approximately $3,500,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the SOUTHERN TIER region and includes the following:
Counties
TIOGA
Towns
BARTON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
State Senatorial District(s)
58th Senatorial District (Thomas F. O'Mara)
State Assembly District(s)
124th Assembly District (Christopher S. Friend)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov