RT 17 PAVEMENT, EXIT 102 TO 103
Project ID No. 906796
Description
This project addresses the pavement and shoulders with a Warm-Mix Asphalt top course, on Route 17, from Exit 102 to 103, in the town of Thompson, Sullivan County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Spring 2028.
- Construction is expected to begin in Spring 2028.
- Construction is expected to be completed in Fall 2028.
Cost of the Project
The project cost is approximately $13,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the SOUTHERN TIER region and includes the following:
Counties
SULLIVAN
Towns
THOMPSON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
State Senatorial District(s)
51th Senatorial District (Peter Oberacker)
State Assembly District(s)
100th Assembly District (Paula Elaine Kay)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov