Project Details

RT 17, LIVINGSTON MANOR TO PARKSVILLE, RESURFACING

Project ID No. 906778 , Contract Number D264502

Description

This project mills and resurfaces Route 17 from Exit 96 to one-half mile east of Exit 97.   Project also mills and resurfaces Exit ramps 96 and 97  Towns of Rockland and Liberty, Sullivan County.

Issue Description:
This project will likely be a 2R Type, due to Cold-in-Place Recycling on a Freeway. 3R Standards would then be needed, with possible Non-Standard Features to address and/or justify. This could delay time to Design Approval, depending on the number and type of NSFs that are identified.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 05/20/2021

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
07/02/2021 11/19/2021 04/01/2022 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$5,333,450 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the SOUTHERN TIER region and includes the following:

Counties
SULLIVAN

Towns
LIBERTY
ROCKLAND

09 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)

State Senatorial District(s)
51th Senatorial District (Peter Oberacker)

State Assembly District(s)
100th Assembly District (Paula Elaine Kay)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 9 Regional Director's Office
44 Hawley Street
Binghamton, NY 13901
Phone: 607-721-8116
Email: r9projects@dot.ny.gov
Provide feedback on this project