Project Details

CULVERT REHAB/REPLACEMENT: ORANGE COUNTY

Project ID No. 8LC121 , Contract Number D265611

Description

This project will rehabilitate, replace, or partially replace eight culverts in Orange County. The rehabilitations will occur on the two culverts that carry NY Route 52 over Twin Ponds and an Unknown Stream, NY Route 32 over Closed Drainage System, and two culverts carrying NY Route 218 over the Clove and Stony Lonesome. The replacements will occur on the culverts carrying Route 218 over Unknown Stream and Crows Nest Brook, and a partial replacement will occur on the culvert carrying Route 207 over Unknown Stream. Work will take place in various municipalities throughout Orange County.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 01/08/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
02/10/2026 12/31/2027 11/30/2027 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$9,207,000 $0 $9,207,000 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ORANGE

Towns
BLOOMING GROVE
CORNWALL
HIGHLANDS
MONTGOMERY
NEW WINDSOR
WOODBURY

Villages
WOODBURY

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)
42th Senatorial District (James Skoufis)

State Assembly District(s)
099th Assembly District (Chris Eachus)
101th Assembly District (Brian Maher)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov