CULVERT REHAB/REPLACEMENTS: PUTNAM AND WESTCHESTER COUNTIES
Project ID No. 8LC111 , Contract Number D265424
Description
This project will rehab or replace seven culverts throughout various municipalities in Putnam and Westchester counties. The replacement work will occur on the culverts that carry NY 100, US 202, NY 117, Saw Mill River Parkway, US Route 6, and NY 6N over Unknown Streams, Gregory Pond, and the Muscoot Reservoir. The rehab will occur on the culvert that carries I-684 over Unknown Stream.
Project Overview
Project Status
- The project has been Under Construction.
- The Bid Opening was on 02/27/2025
Project Schedule
| Award of Contract | Original Contract Completion Date* | Estimated Substantial Completion Date* | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 05/06/2025 | 12/31/2026 | 12/01/2026 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $13,322,365 | $0 | $13,322,365 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
PUTNAM
WESTCHESTER
Towns
CARMEL
CORTLANDT
HARRISON
NEW CASTLE
NORTH SALEM
SOMERS
Villages
HARRISON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
16th Congressional District (George Latimer)
17th Congressional District (Michael Lawler)
State Senatorial District(s)
37th Senatorial District (Shelley B. Mayer)
40th Senatorial District (Pete Harckham)
State Assembly District(s)
093th Assembly District (Chris Burdick)
094th Assembly District (Matt Slater)
095th Assembly District (Dana Levenberg)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov