Project Details

LOWER HUDSON TRANSIT LINK:INTGRTD CRDR MGMNT & RAMP METERING

Project ID No. 882351 , Contract Number D263682

Description

This project is a portion of the Lower Hudson Transit Link along and parallel to the Interstate Route 287 corridor from the Village of Suffern, Rockland County across the new New York Bridge to the City of White Plains in Westchester County. The intention of this project is to reduce the travel delay along the corridor by encouraging the use of public transit. This will occur by means of Ramp Metering and Traffic signal improvements as well as Transit stop improvements. Interstate Route 287 carries between 80,000 and 140,000 vehicles daily and is subject to significant recurring peak hour delays.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/22/2018

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
05/08/2018 11/15/2020 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$55,883,000 $3,912,184 $59,795,184 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ROCKLAND
WESTCHESTER

Towns
CLARKSTOWN
GREENBURGH
ORANGETOWN
RAMAPO

Villages
MONTEBELLO
NYACK
SOUTH NYACK
SPRING VALLEY
SUFFERN
TARRYTOWN
AIRMONT
CHESTNUT RIDGE
ELMSFORD

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
16th Congressional District (George Latimer)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
35th Senatorial District (Andrea Stewart-Cousins)
38th Senatorial District (Bill Weber)

State Assembly District(s)
092th Assembly District (MaryJane Shimsky)
096th Assembly District (Patrick J. Carroll)
097th Assembly District (Aron Wieder)
098th Assembly District (Karl Brabenec)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project