PAVING: ROUTE 9A AND YONKERS AVENUE, TOWN OF GREENBURGH AND CITY OF YONKERS
Project ID No. 881552 , Contract Number D264636
Description
This project will correct existing pavement deficiencies on New York Route 9A (Saw Mill River Road) from Old Nepperhan Avenue (Reference Route 983B) in the City of Yonkers to Lawrence Avenue in the Town of Greenburgh, Village of Hastings-on-Hudson and Yonkers Avenue (Reference Route 984E) from Dunwoodie Street to Bronx River Road in City of Yonkers, Westchester County. The work will primarily consist of milling and filling the roadway and applying a warm-mix asphalt overlay to the road surface to extend its service life and improve the quality and safety of the pavement. Additionally, existing pedestrian facilities will be reconstructed to meet current Americans with Disabilities Act specifications where applicable.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 11/18/2021
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 01/03/2022 | 01/13/2023 | 08/11/2023 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $8,802,000 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
WESTCHESTER
Cities
YONKERS
Towns
GREENBURGH
Villages
HASTINGS-ON-HUDSON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
16th Congressional District (George Latimer)
State Senatorial District(s)
35th Senatorial District (Andrea Stewart-Cousins)
State Assembly District(s)
089th Assembly District (J. Gary Pretlow)
090th Assembly District (Nader J. Sayegh)
092th Assembly District (MaryJane Shimsky)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov