Project Details

RUSTIC RAIL REPLACEMENTS IN ORANGE AND ULSTER COUNTIES

Project ID No. 881531 , Contract Number D264785

Description

This project will replace selected segments of the "rustic", self-oxidizing metal, guiderail on federal aid eligible state highways in various municipalities in Orange and Ulster Counties. The rustic guiderail is showing signs of extensive deterioration and will be replaced with galvanized guide rail to continue to provide the traveling public the intended safety benefits that guiderail provides.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 08/04/2022

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
09/07/2022 12/31/2023 10/01/2024 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$14,153,220 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ORANGE
ULSTER

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)
19th Congressional District (Josh Riley)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)
42th Senatorial District (James Skoufis)
46th Senatorial District (Patricia Fahy)
51th Senatorial District (Peter Oberacker)

State Assembly District(s)
098th Assembly District (Karl Brabenec)
099th Assembly District (Chris Eachus)
100th Assembly District (Paula Elaine Kay)
101th Assembly District (Brian Maher)
102th Assembly District (Chris Tague)
103th Assembly District (Sarahana Shrestha)
104th Assembly District (Jonathan G. Jacobson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project