INTERSTATE 287 PAVING: WESTCHESTER AVENUE TO ROUTE 1
Project ID No. 881489 , Contract Number D265268
Description
This project will resurface Interstate 287, also known as the Cross Westchester Expressway, from the Westchester Avenue interchange to the Route 1 interchange in the Towns of Harrison and Rye, the villages of Harrison, Rye Brook, and Port Chester as well as the Cities of White Plains and Rye in Westchester County. Additionally, on and off ramp resurfacing with the project's limits will be included as determined necessary and feasible within the scope of the project. Work will also include drainage improvements.
Project Overview
Project Status
- The project has been Under Construction.
- The Bid Opening was on 06/06/2024
Project Schedule
| Award of Contract | Original Contract Completion Date* | Estimated Substantial Completion Date* | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 07/18/2024 | 11/30/2025 | N/A |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $32,377,766 | $803,698 | $33,181,464 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
WESTCHESTER
Cities
RYE
WHITE PLAINS
Towns
HARRISON
RYE
Villages
HARRISON
PORT CHESTER
RYE BROOK
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
16th Congressional District (George Latimer)
State Senatorial District(s)
37th Senatorial District (Shelley B. Mayer)
State Assembly District(s)
091th Assembly District (Steven Otis)
093th Assembly District (Chris Burdick)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.