Project Details

ROUTE 9D BREAKNECK TUNNEL IMPROVEMENTS: LIGHTING, PED, STRUCTURAL

Project ID No. 881488 , Contract Number D265238

Description

This project will replace the existing lighting system in the Route 9D Breakneck Tunnel in the Town of Philipstown in Putnam County and the Town of Fishkill in Dutchess County. The project will also include resurfacing of the travel lanes and shoulders through the tunnel, concrete tunnel lining, and pedestrian improvements as well as shoulder reconstruction and widening. Coordination will be necessary with Central Hudson Gas & Electric to mitigate a transmission line within the existing drainage system.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 04/25/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
06/03/2024 09/25/2025 12/01/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,538,522 $1,331,880 $4,870,402 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
PUTNAM

Towns
PHILIPSTOWN

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)

State Assembly District(s)
095th Assembly District (Dana Levenberg)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project