Project Details

SST PAVEMENT SAFETY IMPROVEMENT: HRP & CCP

Project ID No. 881397 , Contract Number D265009

Description

This project will resurface the northbound Hutchison River Parkway lanes from Mamaroneck Avenue to Route 127 and both directions of the Cross County Parkway from New Rochelle Road to the Hutchinson River Parkway interchange. This location was selected through the NYSDOT Skid Accident Reduction Program (SKARP). Pavement at SKARP locations is tested and found to have reduced skid resistance in wet weather conditions. This project is located in the Towns of Scarsdale, Harrison and Eastchester, Villages of Scarsdale and Harrison and the City of White Plains in Westchester County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 04/20/2023

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
06/02/2023 11/23/2023 05/08/2024 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$5,627,797 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
WESTCHESTER

Cities
WHITE PLAINS

Towns
EASTCHESTER
HARRISON
SCARSDALE

Villages
HARRISON
SCARSDALE

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
16th Congressional District (George Latimer)

State Senatorial District(s)
37th Senatorial District (Shelley B. Mayer)

State Assembly District(s)
088th Assembly District (Amy Paulin)
093th Assembly District (Chris Burdick)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project