Project Details

BRIDGE REHABILITATION/REPLACE: WESTCHESTER COUNTY

Project ID No. 881368 , Contract Number D264324

Description

This project will rehabilitate or replace three bridges in Westchester county. The work will include replacing the bridge carrying the Saw Mill River Parkway over State Route 119 in the Town of Greenburgh and in the Village of Elmsford. This project will also rehabilitate the bridge that carries Hospital Road over the Sprain Brook Parkway in the Town of Mount Pleasant and the bridge carrying Ardsley Road over the Sprain Brook Parkway in the Town of Greenburgh.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 01/21/2021

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
03/09/2021 10/03/2023 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$26,544,141 $22,788,234 $49,332,375 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: Yes

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
WESTCHESTER

Cities
YONKERS

Towns
EASTCHESTER
GREENBURGH
MOUNT PLEASANT

Villages
BRONXVILLE
ELMSFORD

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
16th Congressional District (George Latimer)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
35th Senatorial District (Andrea Stewart-Cousins)
37th Senatorial District (Shelley B. Mayer)

State Assembly District(s)
088th Assembly District (Amy Paulin)
090th Assembly District (Nader J. Sayegh)
092th Assembly District (MaryJane Shimsky)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project