Project Details

ROUTE 213 SIDEWALK AND ROAD SETTLEMENT REPAIR - ROSENDALE

Project ID No. 881354 , Contract Number D264283

Description

The embankment slope adjacent to Route 213 directly east and west of Binnewater Road in the Town of Rosendale in Ulster County is unstable and needs corrective action to provide the proper stabilization. The problem is the result of high artesian water levels. As a result, the roadway and sidewalk along Route 213 are settling, requiring the sidewalk within the project limits to be replaced to eliminate safety hazards.  The sidewalk will be brought up to current ADA compliance standards. Additionally, long term stabilization methods will be installed to mitigate the sidewalk and Route 213 settlement.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 08/20/2020

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
09/15/2020 01/22/2021 12/04/2020 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$706,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ULSTER

Towns
ROSENDALE

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
41th Senatorial District (Michelle Hinchey)

State Assembly District(s)
103th Assembly District (Sarahana Shrestha)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project