Project Details

SMPSN MAINTENANCE BY CONTRACT

Project ID No. 881301 , Contract Number D263328

Description

This project will consist of performing maintenance work on facilities and structures designed to collect, store and treat storm water. The work will take place in various municipalities on Routes 66 & 295 in Columbia County, Routes 9, 9G, 55, & 987G ¢TSP! in Dutchess County, Routes 9W, 28, 32, & 209 in Ulster County, Routes 9W, 45, 59, 202, 303, &987C ¢PIP! in Rockland County, Routes 17, 17K, 17M, 32, I-84, 94, 208, 209, 211, & 300 in Orange County, Routes 6, 6N, 9D, 22, I-84, 312, & I-684 in Putnam County and Routes 9, 9A, 22, 35, 119, 133, I-684, 907W ¢HRP!, 987D ¢SMRP!, 987F ¢SBP!, 987G ¢TSP!, & 987H¢BMP! in Westchester County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 01/12/2017

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
N/A 11/30/2018 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$950,491 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: No

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
COLUMBIA
DUTCHESS
ORANGE
PUTNAM
ROCKLAND
ULSTER
WESTCHESTER

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project