Project Details

CULVERTS REHAB/REPLACE

Project ID No. 881214 , Contract Number D262855

Description

Under this project, selected culverts in the counties of Dutchess, Orange, Rockland and Westchester will be subject to replacement or rehabilitation work, as needed, to prevent or address existing drainage problems. Culverts to be worked on will be: C820027 Route 199, C850096 Route 211, C860018 Route 9W, & C890024 Taconic State Parkway.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 06/04/2015

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
07/22/2015 10/31/2016 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,686,737 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
DUTCHESS
ORANGE
ROCKLAND
WESTCHESTER

Towns
MILAN
OSSINING
STONY POINT
WALLKILL

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
17th Congressional District (Michael Lawler)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
40th Senatorial District (Pete Harckham)
41th Senatorial District (Michelle Hinchey)
42th Senatorial District (James Skoufis)

State Assembly District(s)
095th Assembly District (Dana Levenberg)
099th Assembly District (Chris Eachus)
100th Assembly District (Paula Elaine Kay)
106th Assembly District (Didi Barrett)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project