SIGNAL IMPROVEMENTS: DUTCHESS, ULSTER, & WESTCHESTER
Project ID No. 881204 , Contract Number D264286
Description
This project will consist of replacing or installing new traffic control devices at several intersections throughout several municipalities in Dutchess, Ulster, and Westchester Counties. The work will include, but won't be limited to, replacing signals, installing flashing beacons and adding pedestrian signals and crosswalks at the following locations: Route 9 at Pine Woods Road in the Town of Hyde Park, Route 52 at eastbound and westbound exit ramp off I-84 in the Town of Fishkill, Albany Avenue Arterial Highway at Roosevelt Avenue & Foxhall Avenue in the City of Kingston, Route 100 at Route 100A & East Hartsdale Avenue and Route 9A at Old County Road in the Town of Greenburgh, and Route 22 at Olmsted Road & Tompkins Road & Ross Road in the Village and Town of Scarsdale.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 02/18/2021
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 05/06/2021 | 09/15/2022 | 11/01/2023 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $4,662,204 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
DUTCHESS
ULSTER
WESTCHESTER
Cities
KINGSTON
Towns
FISHKILL
GREENBURGH
HYDE PARK
SCARSDALE
Villages
SCARSDALE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
16th Congressional District (George Latimer)
18th Congressional District (Patrick Ryan)
State Senatorial District(s)
35th Senatorial District (Andrea Stewart-Cousins)
37th Senatorial District (Shelley B. Mayer)
39th Senatorial District (Rob Rolison)
41th Senatorial District (Michelle Hinchey)
State Assembly District(s)
088th Assembly District (Amy Paulin)
092th Assembly District (MaryJane Shimsky)
103th Assembly District (Sarahana Shrestha)
105th Assembly District (Anil Beephan, Jr.)
106th Assembly District (Didi Barrett)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov