ROUTE 9W SUBSURFACE AND PAVEMENT REPAIR: NEWBURGH

Project ID No. 823955 , Contract Number D265035

Description

There is a subsurface problem related to soil instability causing pavement failure on Route 9W/Route 32 overlap between the eastbound Interstate 84 ramps and Plank Road (Reference Route 980T).  The problem has created a reoccurring depression in the pavement. A drainage structure within 500 feet to the north of the area with the reoccurring pavement issue requires work to function properly. This project will address the source of the subsurface problem, correct the issue, and repave the affected area of pavement, extend the paving to just north of the Route 9W and Route 32 intersection to correct rutted pavement surfaces as well as improve an existing drainage structure near the subsurface issue location. This project will correct the pavement issue from recurring at this location, decrease pavement conditions that may contribute to motorist lane departures in avoidance of uneven pavement surfaces and the potential for crashes that lane departure could contribute to, as well as improve the function of a drainage structure between the eastbound Interstate 84 on-ramp and the Interstate 84 off-ramp to US Route 9W in the northbound direction in the Town of Newburgh and City of Newburgh in Orange County. The project will also include traffic signal improvements.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 05/18/2023

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
07/05/2023 12/31/2023 12/01/2023 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,645,164 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ORANGE

Cities
NEWBURGH

Towns
NEWBURGH

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)

State Assembly District(s)
104th Assembly District (Jonathan G. Jacobson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project