Project Details

PAVING: ROUTES 209, 199 AND 32 - TOWN OF ULSTER

Project ID No. 817751 , Contract Number D264603

Description

This project will correct pavement deficiencies that exist on State Routes 199, 209 and 32 in Ulster County. The limits of the project on Routes US 209 and NY 199 are from the Catskill Mountain Railroad crossing to Route 32 (Flatbush Road) and the work on NY Route 32 (Flatbush Road) will be at the interchange at NY Route 199 in the Town of Ulster. The work will primarily consist of milling the existing pavement and filling the roadway back in to the same depth by applying an asphalt overlay to the road surface to extend its service life and improve the quality and safety of the pavement.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 10/21/2021

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
11/24/2021 08/31/2022 11/21/2022 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$7,846,906 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ULSTER

Towns
ULSTER

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)

State Senatorial District(s)
41th Senatorial District (Michelle Hinchey)

State Assembly District(s)
103th Assembly District (Sarahana Shrestha)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov