Project Details

ROUTE 22 RESURFACING IN DUTCHESS AND PUTNAM

Project ID No. 813131 , Contract Number D265125

Description

This project will resurface segments of Route 22 from north of the Interstate 84/684 interchange to Route 55 in Dutchess and Putnam Counties. Route 22 is identified as a part of the NYS Freight Core Highway Network from Route 55 in Dutchess County to I-84 in Putnam County along the east side of the Hudson Valley Region. This corridor provides freight connection between the urban area of Poughkeepsie and the State of Connecticut via I-84 Eastbound and Westchester County via I-684.  Trucks account for 8% of the average annual daily traffic within the corridor. The work will take place in the Towns of Southeast, Pawling and Patterson and the Village of Brewster.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 12/14/2023

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
01/16/2024 08/31/2024 10/21/2024 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$14,864,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
DUTCHESS
PUTNAM

Towns
PATTERSON
PAWLING
SOUTHEAST

Villages
PAWLING
BREWSTER

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)
40th Senatorial District (Pete Harckham)

State Assembly District(s)
094th Assembly District (Matt Slater)
105th Assembly District (Anil Beephan, Jr.)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project