Project Details

REGION 8 PEDESTRIAN SAFETY ACTION PLAN CONTRACT #3

Project ID No. 80PS04 , Contract Number D264056

Description

The Project will identify and improve pedestrian safety in urban areas as described in the June 20, 2016 New York State Pedestrian Safety Action Plan available on the website. The project proactively addresses safety issues and reduces crash potential by implementing countermeasures at locations that have shown to be high risk. The project includes installation of signalized intersection improvements including, but not necessarily limited to high visibility crosswalk markings, countdown pedestrian indications, latching pushbuttons, accessible pedestrian signals (APS), new pedestrian signals, and turning vehicle yield to pedestrian signs. This Contract will address Signalized intersections in Dutchess County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 10/10/2019

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
11/15/2019 12/31/2020 12/01/2020 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,983,740 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
DUTCHESS

Cities
POUGHKEEPSIE

Towns
POUGHKEEPSIE
RED HOOK

Villages
RED HOOK

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)
41th Senatorial District (Michelle Hinchey)

State Assembly District(s)
103th Assembly District (Sarahana Shrestha)
104th Assembly District (Jonathan G. Jacobson)
106th Assembly District (Didi Barrett)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project