Project Details

ROUTE 17 AT EXIT 122 STAGE II

Project ID No. 806510 , Contract Number D265297

Description

This interchange reconstruction project is the second phase of a project to increase safety and mobility on NYS Route 17 in proximity to the interchange with Crystal Run Road, East Main Street. The project will complete the reconstruction of the Exit 122 interchange to meet interstate standards for design, as the entirety of Route 17 is designated to be converted to Interstate 86. Work includes new ramps on the Westbound side of Route 17 to Crystal Run Road and to Interstate 84 Eastbound, and to improve the ramp from Crystal Run Road to Route 17 Eastbound. Work will also include pedestrian improvements including a shared use path along Crystal run road, the widening of the NY Route 17 over the Wallkill River bridge, and signal improvements where necessary. This project is located in the Town of Wallkill in Orange County.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 12/19/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
02/24/2025 12/20/2026 11/20/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$67,841,000 $1,041,371 $68,882,371 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ORANGE

Towns
WALLKILL

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
42th Senatorial District (James Skoufis)

State Assembly District(s)
100th Assembly District (Paula Elaine Kay)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov