ROUTE 17 SLOATSBURG COMPLETE STREETS/INFRASTRUCTURE IMPROVEMENT
Project ID No. 806507 , Contract Number D264085
Description
The Project will develop a complete streets concept for the Route 17 corridor based on feedback received from Public Workshops. Considering public input and comments will produce a project that meets the objectives and goals of the community while improving safety, efficiency and balance on Route 17 and in the greater Sloatsburg community. This project is located in the Village of Sloatsburg, Town of Ramapo, Rockland County and Town of Tuxedo, Orange County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 01/16/2020
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 03/06/2020 | 11/23/2021 | 11/08/2021 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $10,859,071 | $31,627 | $10,890,698 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: Yes
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
ORANGE
ROCKLAND
Towns
RAMAPO
TUXEDO
Villages
SLOATSBURG
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
17th Congressional District (Michael Lawler)
18th Congressional District (Patrick Ryan)
State Senatorial District(s)
38th Senatorial District (Bill Weber)
42th Senatorial District (James Skoufis)
State Assembly District(s)
098th Assembly District (Karl Brabenec)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov