Project Details

PAVING: INTERSTATE 84 - BOWEN ROAD OVERPASS TO CONNECTICUT STATE LINE

Project ID No. 806255 , Contract Number D264612

Description

This project will correct pavement deficiencies found on a segment of Interstate 84, from the Bowen Road overpass in the Town of Kent, through the Town of Patterson, to the Connecticut State line in the Town of Southeast in Putnam County. Additional work will include resurfacing the interchange ramps for Ludingtonville Road, Route 311, Route 312, Route 121, and Connecticut Exit 1 (Saw Mill Road). The work will primarily consist of milling the top layer of existing asphalt and overlaying the roadway with warm-mix asphalt to extend its service life and improve the quality and safety of the pavement. This project also includes resurfacing the eastbound and westbound Stormville Rest Area parking lots in the Town of East Fishkill in Dutchess County. In addition to resurfacing work, minor drainage and other subsurface repairs will be done as well.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 11/04/2021

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
01/07/2022 11/30/2022 10/31/2022 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$17,511,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
DUTCHESS
PUTNAM

Towns
EAST FISHKILL
PATTERSON
SOUTHEAST
KENT

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)
40th Senatorial District (Pete Harckham)

State Assembly District(s)
094th Assembly District (Matt Slater)
105th Assembly District (Anil Beephan, Jr.)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project