Project Details

ROUTE 59 AND ROUTE 202 CORRECTIVE PAVEMENT TREATMENTS

Project ID No. 803045 , Contract Number D263046

Description

This project will resurface a segment of Route 59 from Route 17 to Route 202 and from Route 202 to 0.2 miles west of Hemion Road, as well as a segment of Route 202 from the New Jersey line to Route 59, all in the Villages of Hillburn and Suffern, Town of Ramapo in Rockland County. The project will include milling and resurfacing of existing asphalt pavement and the restoration of pavement markings. As well some drainage work may be preformed to include the cleaning and repair of some drainage basins.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 12/03/2015

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
01/21/2016 07/31/2016 11/08/2016 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$2,457,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ROCKLAND

Towns
RAMAPO

Villages
SUFFERN

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
17th Congressional District (Michael Lawler)

State Senatorial District(s)
38th Senatorial District (Bill Weber)

State Assembly District(s)
098th Assembly District (Karl Brabenec)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project