Project Details

ROUTE 28/ESOPUS CREEK-BRIDGE REPLACEMENT - BIN 1091290

Project ID No. 801846 , Contract Number D264093

Description

This project will replace the State Route 28 Bridge over the Esopus Creek between Route 212 and Riseley Road with a bridge that does not have piers or abutments within the creek. Route 28 is located in a valley within the Catskill Park and runs parallel to the Esopus Creek. Due to the proximity and elevation to the creek the bridge is susceptible to flash flooding, very fast flowing and quickly rising water levels that cause scour around the bridge support piers located within the creek. After every significant rain fall the bridge is regularly closed for safety concerns that require inspection and normally result in emergency aid and follow-up emergency repair. Bridge is located in Hamlet of Mount Tremper within the Town of Shandaken, Ulster County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 01/16/2020

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
02/27/2020 09/30/2021 10/22/2021 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$23,643,236 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ULSTER

Towns
SHANDAKEN

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)

State Senatorial District(s)
41th Senatorial District (Michelle Hinchey)

State Assembly District(s)
102th Assembly District (Chris Tague)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project