Project Details

BROADWAY PEDESTRIAN & TRAFFIC SIGNAL IMPROVEMENTS

Project ID No. 800526

Description

The project objective is to upgrade sidewalks and curb ramps and replace existing traffic signals along Broadway between Robinson Avenue (Route 9W) and Grand Street to meet Americans with Disabilities Act Accessibility Guidelines (ADAAG). The project will replace six non-standard traffic signals at Broadway intersecting Robinson Avenue, Concord Street/Mill Street, William Street/Dubois Street, Johnston Street, Liberty Street and Grand Street. Sidewalks and curb ramps will be replaced at all curb corners on both sides of Broadway. Sidewalk curb extensions will be implemented to improve pedestrian access and safety throughout the corridor. In total, approximately 5,600 square yards of new sidewalk will be installed. Landscaping and utilities may be upgraded on an as needed basis.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 08/29/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
11/12/2024 N/A N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
N/A N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: Yes

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the HUDSON VALLEY region and includes the following:

Counties
ORANGE

Cities
NEWBURGH

08 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)

State Senatorial District(s)
39th Senatorial District (Rob Rolison)

State Assembly District(s)
104th Assembly District (Jonathan G. Jacobson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 8 Regional Director's Office
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov
Provide feedback on this project