BROADWAY PEDESTRIAN & TRAFFIC SIGNAL IMPROVEMENTS
Project ID No. 800526
Description
The project objective is to upgrade sidewalks and curb ramps and replace existing traffic signals along Broadway between Robinson Avenue (Route 9W) and Grand Street to meet Americans with Disabilities Act Accessibility Guidelines (ADAAG). The project will replace six non-standard traffic signals at Broadway intersecting Robinson Avenue, Concord Street/Mill Street, William Street/Dubois Street, Johnston Street, Liberty Street and Grand Street. Sidewalks and curb ramps will be replaced at all curb corners on both sides of Broadway. Sidewalk curb extensions will be implemented to improve pedestrian access and safety throughout the corridor. In total, approximately 5,600 square yards of new sidewalk will be installed. Landscaping and utilities may be upgraded on an as needed basis.
Project Overview
Project Status
- The project has been Under Construction.
- The Bid Opening was on 08/29/2024
Project Schedule
| Award of Contract | Original Contract Completion Date* | Estimated Substantial Completion Date* | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 11/12/2024 | N/A | N/A |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| N/A | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: Yes
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
ORANGE
Cities
NEWBURGH
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)
State Senatorial District(s)
39th Senatorial District (Rob Rolison)
State Assembly District(s)
104th Assembly District (Jonathan G. Jacobson)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov