NY 17A/LONG HOUSE CREEK BRIDGE: ORANGE COUNTY
Project ID No. 800225
Description
This project will replace the existing structure that carries State Route 17A over the Long House Creek in the Town of Warwick in Orange County. This bridge replacement project will improve resiliency by constructing the new abutments where they will no longer be susceptible to undermining.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2026/2027.
- Construction is expected to begin in Spring 2027.
- Construction is expected to be completed in Spring 2029.
Cost of the Project
The project cost is approximately $19,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the HUDSON VALLEY region and includes the following:
Counties
ORANGE
Towns
WARWICK
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
18th Congressional District (Patrick Ryan)
State Senatorial District(s)
42th Senatorial District (James Skoufis)
State Assembly District(s)
098th Assembly District (Karl Brabenec)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
4 Burnett Boulevard
Poughkeepsie, NY 12603
Phone: 845-431-5750
Email: dot.sm.r08.nysdot@dot.ny.gov