Project Details

ADA ACCESSIBILITY IMPROVEMENTS 2028

Project ID No. 780768

Description

This project will make improvements to existing sidewalk curb ramps to improve access for disabled persons. This project is located in various counties within Region 7.

Project Overview

Project Status

  • The current status of the project is In Development.
  • The Bid Opening is expected to be in Winter 2027/2028.
  • Construction is expected to begin in Spring 2028.
  • Construction is expected to be completed in Winter 2028/2029.

Cost of the Project

The project cost is approximately $1,200,000 .

This project receives funding from the following sources:

Federal: Yes

State : Yes

Local : No

The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.

Location

This project is located in the NORTH COUNTRY region and includes the following:

Counties
CLINTON
FRANKLIN
JEFFERSON
LEWIS
ST LAWRENCE

07 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Morgan Zell
317 Washington Street
Watertown, NY 13601
Phone: 518-457-6720
Email: Morgan.Zell@dot.ny.gov
Provide feedback on this project