CULVERT REPAIRS

Project ID No. 780711

Description

This project will perform culvert repairs at locations to be determined by the Regional Structures Management Team. Locations may include all counties in Region 7.

Project Overview

Project Status

  • The current status of the project is In Development.
  • The Bid Opening is expected to be in Fall 2027.
  • Construction is expected to begin in Winter 2027/2028.
  • Construction is expected to be completed in Summer 2028.

Cost of the Project

The project cost is approximately $7,500,000 .

This project receives funding from the following sources:

Federal: Yes

State : Yes

Local : No

The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.

Location

This project is located in the NORTH COUNTRY region and includes the following:

Counties
ST LAWRENCE

Towns
DE KALB
OSWEGATCHIE
STOCKHOLM

07 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
45th Senatorial District (Daniel G. Stec)
49th Senatorial District (Mark Walczyk)

State Assembly District(s)
116th Assembly District (Scott Gray)
117th Assembly District (Ken Blankenbush)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Morgan Zell
317 Washington Street
Watertown, NY 13601
Phone: 518-457-6720
Email: Morgan.Zell@dot.ny.gov
Provide feedback on this project