Project Details

PAVEMENT MARKINGS - SFY 2028/29

Project ID No. 680692

Description

A project to perform pavement markings and rumble strip applications at various locations in one or more of the following counties: Allegany, Chemung, Schuyler, Steuben and Yates.

Project Overview

Project Status

  • The current status of the project is In Development.
  • The Bid Opening is expected to be in Winter 2028/2029.
  • Construction is expected to begin in Spring 2029.
  • Construction is expected to be completed in Fall 2029.

Cost of the Project

The project cost is approximately $3,300,000 .

This project receives funding from the following sources:

Federal: Yes

State : Yes

Local : No

The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.

Location

This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:

Counties
ALLEGANY
CHEMUNG
SCHUYLER
STEUBEN
TIOGA
YATES

06 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
107 Broadway
Hornell, NY 14843
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov
Provide feedback on this project