GUIDERAIL REPAIR & REPLACEMENT - SFY 2025/26

Project ID No. 680622 , Contract Number D265706

Description

A project to address needed guiderail repairs and upgrades at various locations in one or more of the following counties: Allegany, Chemung, Schuyler, Steuben and Yates.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 02/05/2026

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
03/09/2026 12/10/2026 07/08/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$516,670 ($35,329) $481,341 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:

Counties
ALLEGANY
CHEMUNG
STEUBEN
WYOMING

Towns
AMITY
CATLIN
CLARKSVILLE
CUBA
GENESEE
GENESEE FALLS
HUME
PULTENEY

06 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
24th Congressional District (Claudia Tenney)

State Senatorial District(s)
57th Senatorial District (George M. Borrello)
58th Senatorial District (Thomas F. O'Mara)

State Assembly District(s)
132th Assembly District (Philip A. Palmesano)
147th Assembly District (David DiPietro)
148th Assembly District (Joe Sempolinski)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
107 Broadway
Hornell, NY 14843
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov