NY 36 HORNELL GATEWAY CONNECTOR PROJECT (PHASE II)
Project ID No. 609645
Description
Reconstruction and Modernization of NY 36 and new pedestrian facilities between Broadway Street and Adsit Street in the City of Hornell and Town of Hornellsville, Steuben County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Spring 2027.
- Construction is expected to begin in Summer 2027.
- Construction is expected to be completed in Summer 2028.
Cost of the Project
The project cost is approximately $34,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:
Counties
STEUBEN
Cities
HORNELL
Towns
HORNELLSVILLE
Villages
NORTH HORNELL
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
State Senatorial District(s)
58th Senatorial District (Thomas F. O'Mara)
State Assembly District(s)
132th Assembly District (Philip A. Palmesano)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: