Project Details

I-86 MILL AND FILL, HORSEHEADS TO ELMIRA

Project ID No. 606762 , Contract Number D265752

Description

A project to perform paving on I-86 between Horseheads and Elmira, I-86 on and off ramps for Church and Water Street and on NY 352/East Church Street from I-86 to Judson Street in the towns of Horseheads and Elmira, Chemung County

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/12/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
04/10/2026 11/01/2026 11/01/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$5,957,054 $0 $5,957,054 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:

Counties
CHEMUNG

Cities
ELMIRA

Towns
ELMIRA
HORSEHEADS

06 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)

State Senatorial District(s)
58th Senatorial District (Thomas F. O'Mara)

State Assembly District(s)
124th Assembly District (Christopher S. Friend)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
107 Broadway
Hornell, NY 14843
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov
Provide feedback on this project