Project Details

NY 417 OVER DUFFY HOLLOW CREEK BRIDGE, BIN 1012500

Project ID No. 605637 , Contract Number D265897

Description

A project to replace the bridge on NY 417 over Duffy Hollow Creek in the town of Wellsville, Allegany County.

Project Overview

Project Status

  • The current status of the project is In Development.
  • The Bid Opening is expected to be in Fall 2026.
  • Construction is expected to begin in Winter 2026/2027.
  • Construction is expected to be completed in Winter 2027/2028.

Cost of the Project

The project cost is approximately $4,150,000 .

This project receives funding from the following sources:

Federal: Yes

State : Yes

Local : No

The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.

Location

This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:

Counties
ALLEGANY

Towns
WELLSVILLE

06 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)

State Senatorial District(s)
58th Senatorial District (Thomas F. O'Mara)

State Assembly District(s)
148th Assembly District (Joe Sempolinski)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
107 Broadway
Hornell, NY 14843
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov
Provide feedback on this project