NY 19 MBC PAVING - CANEADEA TO SOUTH FILLMORE LINE
Project ID No. 601452 , Contract Number D263932
Description
A maintenance paving project on NY 19 from NY 243 in Caneadea to 1000' north of Tucker Hill Rd in Houghton and from 750' north of CR 35 in Houghton north to the south Fillmore village line in the towns of Caneadea and Hume, and drainage work on NY 417 from Powerhouse Rd to Salt Rising Rd in the town of Genesee, Allegany county.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 04/11/2019
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 05/23/2019 | 08/15/2020 | 09/18/2020 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $7,181,455 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the SOUTHERN TIER/CENTRAL NEW YORK region and includes the following:
Counties
ALLEGANY
Towns
CANEADEA
GENESEE
HUME
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
State Senatorial District(s)
57th Senatorial District (George M. Borrello)
State Assembly District(s)
148th Assembly District (Joe Sempolinski)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: