LG CULVERT PRESERVATION & RENEWAL; SOUTHERN (CATTARAUGUS) - CROSS PROGRAM
Project ID No. 5LC115
Description
This project will replace one deteriorating culvert in the Town of Perrysburg, Cattaraugus County. Anticipate culvert being replaced with a bridge structure.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Fall 2027.
- Construction is expected to begin in Winter 2027/2028.
- Construction is expected to be completed in Fall 2028.
Cost of the Project
The project cost is approximately $9,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the WESTERN NEW YORK region and includes the following:
Counties
CATTARAUGUS
Towns
PERRYSBURG
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
State Senatorial District(s)
57th Senatorial District (George M. Borrello)
State Assembly District(s)
148th Assembly District (Joe Sempolinski)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: