Description
Large Culvert Replacements, NY Rte.5 (BIN 1081430, FORMERLY CIN 540005) NY Rte. 18 (BIN 1081410, FORMERLY CIN 550014) Towns of Evans & Newfane; Erie & Niagara Counties.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Fall 2026.
- Construction is expected to begin in Winter 2026/2027.
- Construction is expected to be completed in Summer 2029.
Cost of the Project
The project cost is approximately $6,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the WESTERN NEW YORK region and includes the following:
Counties
CATTARAUGUS
CHAUTAUQUA
ERIE
NIAGARA
Towns
AURORA
ELLERY
EVANS
LEWISTON
LOCKPORT
NEWFANE
ORCHARD PARK
PERRYSBURG
POLAND
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
24th Congressional District (Claudia Tenney)
26th Congressional District (Timothy Kennedy)
State Senatorial District(s)
57th Senatorial District (George M. Borrello)
60th Senatorial District (Patrick M. Gallivan)
62th Senatorial District (Robert G. Ortt)
State Assembly District(s)
142th Assembly District (Patrick Burke)
144th Assembly District (Paul A. Bologna)
145th Assembly District (Angelo J. Morinello)
147th Assembly District (David DiPietro)
148th Assembly District (Joe Sempolinski)
150th Assembly District (Andrew M. Molitor)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: