ADA COMPLIANCE PROJECT; CATTARAUGUS & CHAUTAUQUA COS.; SFY 24/25

Project ID No. 581625 , Contract Number D265345

Description

This project will improve pedestrian mobility by bringing various locations into compliance with the Americans with Disabilities Act (ADA) requirements for accessibility. The work will include curb ramp installations/upgrades and sidewalk reconstruction.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 10/24/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
N/A 04/30/2026 03/31/2026 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$428,156 ($10,344) $417,812 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the WESTERN NEW YORK region and includes the following:

Counties
CATTARAUGUS
CHAUTAUQUA

05 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)

State Senatorial District(s)
57th Senatorial District (George M. Borrello)

State Assembly District(s)
148th Assembly District (Joe Sempolinski)
150th Assembly District (Andrew M. Molitor)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Ryan Whalen
100 Seneca Street
Buffalo, NY 14203
Phone: 716-847-3239
Email: ryan.whalen@dot.ny.gov
Provide feedback on this project