This project will include traffic signal equipment installation & improvements at various locations in Cattaraugus, Chautauqua, Erie & Niagara Counties.
Project Overview
Project Status
- The current status of the project is Future Development.
- The Bid Opening is expected to be in Fall 2028.
- Construction is expected to begin in Winter 2028/2029.
Cost of the Project
The project cost is approximately $1,050,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the WESTERN NEW YORK region and includes the following:
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.