Project Details

CENTER STREET (NY 353) RECONSTRUCTION; NY 417 TO CTY LINE

Project ID No. 545212

Description

This project will reconstruct Center Street (NY 353) in the city of Salamanca and SNI in Cattaraugus County.

Project Overview

Project Status

  • The current status of the project is In Development.
  • The Bid Opening is expected to be in Summer 2028.
  • Construction is expected to begin in Fall 2028.
  • Construction is expected to be completed in Summer 2029.

Cost of the Project

The project cost is approximately $5,500,000 .

This project receives funding from the following sources:

Federal: Yes

State : Yes

Local : No

The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.

Location

This project is located in the WESTERN NEW YORK region and includes the following:

Counties
CATTARAUGUS

Cities
SALAMANCA

Towns
SALAMANCA

05 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)

State Senatorial District(s)
57th Senatorial District (George M. Borrello)

State Assembly District(s)
148th Assembly District (Joe Sempolinski)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Ryan Whalen
100 Seneca Street
Buffalo, NY 14203
Phone: 716-847-3239
Email: ryan.whalen@dot.ny.gov
Provide feedback on this project