US 20A; US 20 - CENTRE DR
Project ID No. 501026
Description
This project will be resurfacing pavement on Route 20A, from US 20 to Centre Drive, in the Towns of Hamburg and Orchard Park, in Erie County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Spring 2029.
- Construction is expected to begin in Spring 2029.
- Construction is expected to be completed in Winter 2029/2030.
Cost of the Project
The project cost is approximately $2,200,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the WESTERN NEW YORK region and includes the following:
Counties
ERIE
Towns
HAMBURG
ORCHARD PARK
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
State Senatorial District(s)
60th Senatorial District (Patrick M. Gallivan)
State Assembly District(s)
142th Assembly District (Patrick Burke)
147th Assembly District (David DiPietro)
149th Assembly District (Jonathan Rivera)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: