Project Details

STAND-BY STRUCTURES REPAIR CONTRACT FOR 2023, 2024, and 2025

Project ID No. 4T3923 , Contract Number D264828

Description

Stand-By Structures Repair Contract for 2023, 2024, and 2025 - Regionwide. This project will provide treatments or rehabilitation to address unexpected structures problems that may arise.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 07/07/2022

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
08/12/2022 09/16/2025 04/29/2025 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$1,380,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the GENESEE VALLEY region and includes the following:

Counties
GENESEE
LIVINGSTON
MONROE
ONTARIO
ORLEANS
WAYNE
WYOMING

04 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
23th Congressional District (Nicholas Langworthy)
24th Congressional District (Claudia Tenney)
25th Congressional District (Joseph Morelle)

State Senatorial District(s)
54th Senatorial District (Pamela Helming)
55th Senatorial District (Samra G. Brouk)
56th Senatorial District (Jeremy Cooney)
57th Senatorial District (George M. Borrello)
59th Senatorial District (Kristen Gonzalez)
61th Senatorial District (Jeremy J. Zellner)
62th Senatorial District (Robert G. Ortt)

State Assembly District(s)
130th Assembly District (Brian Manktelow)
131th Assembly District (Jeff Gallahan)
133th Assembly District (Andrea K. Bailey)
134th Assembly District (Josh Jensen)
135th Assembly District (Jen Lunsford)
136th Assembly District (Sarah Clark)
137th Assembly District (Demond Meeks)
138th Assembly District (Harry B. Bronson)
139th Assembly District (Stephen Hawley)
144th Assembly District (Paul A. Bologna)
147th Assembly District (David DiPietro)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
1530 Jefferson Road
Rochester, NY 14623
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov
Provide feedback on this project